Rationing of resources and time spent on work performed as part of construction and technical expertise
https://doi.org/10.24412/2409-4358-2022-4-41-50
Abstract
The article is devoted to the methodological provisions of rationing the time and resources spent on performing works and activities as part of construction and technical expertise, which can be judicial, pre-trial and corporate. Regardless of the institutional affiliation, the prospects for developing standards for individual works and activities, as well as enlarged standards for the entire complex of construction and technical expertise procedures are indicated. The development of such standards should be carried out in accordance with the current provisions of regulatory documents and generally accepted methodological principles in the field of technical and estimated rationing. In this regard, the authors point out that in accordance with this approach, a single norm should contain the cost of working time, material and technical resources, and should also be linked to the quantitative and qualification composition of performers. The development of an enlarged norm on the ETS should be carried out by means of calculation based on individual norms. It is noted that these procedures should take into account the use of information models of capital construction objects during construction and technical expertise.
The authors also developed and present in the article the topology of the network schedule of construction and technical expertise, which indicates the sequential nature of the addition of activities and works. This fact indicates the potential of using Informatization in this subject area
The practical significance of the provisions given in the article is related to the development of individual and enlarged standards for work, activities, procedures as part of construction and technical expertise, which should contribute to the possibility of planning this type of activity both on a time scale and in the context of costs and, as a result, making adequate and transparent management decisions. It is also obvious that the use of information models will help reduce the cost and time of construction and technical expertise. This fact must be taken into account when rationing this type of activity.
About the Authors
N. V. LazarevaRussian Federation
Natalia Valerievna Lazareva – Candidate of Technical Sciences
Scopus ID: 57203959777
127051, Moscow, Sadovaya-Samotechnaya str., 10, p. 1
A. Yu. Zinoviev
Russian Federation
Alexander Yurievich Zinoviev – Candidate of Technical Sciences
38 Bolshaya Semenovskaya str., Moscow, 107023
References
1. Simanovich V.M., Ermolaev E.E. Osushestvlenie stroitel`stva, rekonstrukcii, kapital`nogo remonta ob`ecta kapital`nogo stroitel`stva [Implementation of construction, reconstruction, capital repairs of the capital construction object] // Normirovanie i oplata truda v stroitel`stve [Rationing and payment of labor in construction]. 2018. No. 12. Pp. 4-8. URL: https://panor.ru/articles/osushchestvlenie-stroitelstva-rekonstruktsii-kapitalnogo-remonta-obekta-kapitalnogo-stroitelstva/12697.html (In Russian)
2. Ermolaev E.E. Metodologicheskie aspekti novoy modeli razvitiya stroitel`nogo kompleksa [Methodological aspects of the new model of development of the construction Complex] // Internet-zhurnal Naukovedenie [The online journal of the sociology of Science]. 2014. No. 1 (20). Pp. 34. URL: https://cyberleninka.ru/article/n/metodologicheskie-aspekty-novoy-modeli-razvitiya-stroitelnogo-kompleksa (In Russian)
3. Aleksanin A.V. Osobennosti vliyaniya vneshnih faktorov na stroitel`niy ob`ect [Features of the influence of external factors on the construction Object] // Nauchnoe obozrenie [Scientific review]. 2017. No. 6. Pp. 12-15. (In Russian)
4. Aleksanin A.V. Perspektivnie napravleniya razvitiya organizacii stroitel`stva [Perspective directions of development of construction organization] // Nauchnoe obozrenie [Scientific review]. 2015. No. 10-1. Pp. 378-381. URL: http://council.gov.ru/activity/activities/parliamentary/135493/ (In Russian)
5. Yazhlev I.K., Popkov A.G., Belogurova O.A. Problemi normativno-pravovogo obespecheniya vnedreniya resurso-, energosberegayushih tehnologiy v gradostroitel`noy deyatel`nosti [Problems of regulatory support for the introduction of resource-and energy-saving technologies in urban development] // Ekonomika I predprinimatel`stvo [Economics and entrepreneurship]. 2020. No. 3 (116). Pp. 1000-1002. URL: https://www.elibrary.ru/item.asp?id=42812452 (In Russian)
6. Burenin V.S., Yezersky V.A., Monastyrev P.V. Issledovanie sovremennih tendenciy proektirovaniya zhilih zdaniy v Rossii i za rubezhom [Research of modern trends in the design of residential buildings in Russia and abroad] // Arhitektura I vremya [Architecture and time]. 2017. No. 5. Pp. 2. URL: https://www.tstu.ru/book/elib/pdf/sborniki/2017/zaoch_konfer.pdf (In Russian)
7. Klychnikov R.Yu., Monastyrev P.V., Yezersky V.A. Zavisimost` ekonomicheskoy effektivnosti termomodernizacii gruppi zhilih zdaniy ot tempo vee realizacii [Dependence of the economic efficiency of thermal modernization of a group of residential buildings on the pace of its implementation] // V sbornike: fundamental`nie, poiskovie I prikladnie issledovaniya RAASN po nauchnomu obespecheniyu razvitiya arhitekturi, gradostroitel`stva I stroitel`noy otrasli Rossiyskoy Federacii v 2017 godu [In the collection: Fundamental, search and applied research of the Russian Academy of Sciences on scientific support for the development of architecture, urban planning and the construction industry of the Russian Federation in 2017] // Sbornik nauchnih trudov Rossiyskoy akademii arhitekturi I stroitel`nih nauk [Collection of scientific papers of the Russian Academy of architecture and construction Sciences]. 2018. Pp. 254-264. URL: https://www.elibrary.ru/item.asp?id=41280859 (In Russian)
8. Klyuev V.D., Zaitsev D.A., Zhuravlev P.A. Normativnaya baza dlya stoimostnoy ocenki kapital`nogo remonta mnogokvartirnih domov [Normative base for cost estimation of capital repairs of multi-apartment buildings]. 2015. No. 1. URL: http://pgs1923.ru/ru/index.php?m=4&y=2021&v=02&p=08 (In Russian)
9. Sborshchikov S.B., Zhuravlev P.A. Nomenklatura rabot I zatrat na obespechenie kachestva stroitel`noy produkcii I metodi ee identifikacii [Nomenclature of works and costs for ensuring the quality of construction products and methods of its identification] // Normirovanie I oplata truda v stroitel`stve [Rationing and payment of labor in construction]. 2018. No. 3. Pp. 69-73. URL: https://panor.ru/articles/nomenklatura-rabot-i-zatrat-na-obespechenie-kachestva-stroitelnoy-produktsii-i-metody-ee-identifikatsii/12459.html (In Russian)
10. Zhuravlev P.A., Sborshchikov S.B. K voprosu ispol`zovaniya resursno-tehnologicheskogo modelirovaniya pri formirovanii investicionnih program [On the use of resource and technological modeling in the formation of investment programs] // Vestnik Belgorodskogo gosudarstvennogo tehnologicheskogo universiteta im. V.G. Shuhova [Bulletin of the Belgorod state technological University named after V.G. Shukhov]. 2017. No. 7. Pp. 198-201. URL: https://cyberleninka.ru/article/n/k-voprosu-ispolzovaniya-resursno-tehnologicheskogo-modelirovaniya-pri-formirovanii-investitsionnyh-programm (In Russian)
11. Zhuravlev P.A. Nomenklatura trebuemih ob`ektov kapital`- nogo stroitel`stva dlya resursno-tehnologicheskogo modelirovaniya [Nomenclature of required capital Construction objects for resource and technological modeling] // Promishlennoe I grazhdanskoe stroitel`stvo [Industrial and civil construction]. 2020. No. 7. Pp. 52-57. URL: https://www.elibrary.ru/item.asp?id=43801266 (In Russian)
12. Sborshchikov S.B., Lazareva N.V., Bakhus E.E. K voprosu modernizacii system obespecheniya kachestva stroitel`stva ob`ktov yadernoy energetiki [On the issue of modernization of quality assurance systems for construction of nuclear power Facilities] // Vestnik grazhdanskih inzhenerov [Bulletin of civil engineers]. 2019. No. 1 (72). Pp. 219-225. URL: https://vestnik.spbgasu.ru/article/k-voprosu-modernizacii-sistem-obespecheniya-kachestva-stroitelstva-obektov-yadernoy (In Russian)
13. Sborshchikov S.B., Bacchus E.E. Mnogofaktornaya parametricheskaya model` effektivnosti organizacionnih resheniy po obespecheniyu kachestva stroitel`stva [Multi-Factor parametric model of efficiency of organizational decisions to ensure the quality of construction] // I grazhdanskoe stroitel`stvo [Industrial and civil construction]. 2018. No. 12. Pp. 60-67. URL: https://www.elibrary.ru/item.asp?id=36777783 (In Russian)
14. Lyapin A.V., Lyapin V.Yu. Sovremenniy podhod k organizacii smetnoy deyatel`nosti v stroitel`stve [Modern approach to the organization of estimate activity in construction] // Nauchnoe obozrenie [Scientific review]. 2016. No. 8. Pp. 251-255. URL: https://www.elibrary.ru/contents.asp?issueid=1584895 (In Russian)
15. Sborshchikov S.B., Lazareva N.V. Formirovanie dopolnitel`- nogo effekta pri upravlenii stoimost`yu investicionnogo proekta za schet meropriyatiy reinzhiniringa [Formation of an additional effect in managing the cost of an investment project through reengineering activities] // Vestnik grazhdanskih inzhenerov [Bulletin of civil engineers]. 2020. No. 2 (79). Pp. 252-263. URL: https://www.elibrary.ru/item.asp?id=43071753 (In Russian)
16. Sborshchikov S.B., Maslova L.A., Zhuravlev P.A. Reinzhiniring v stroitel`stve [Reengineering in construction] // Promishlennoe I grazhdanskoe stroitel`stvo [Industrial and civil construction]. 2019. No. 7. Pp. 71-76. URL: https://www.elibrary.ru/item.asp?id=38587927 (In Russian)
17. Zharov Ya.V. Organizacionno-tehnologicheskoe proektirovanie v stroitel`stve na osnove intellectual`nogo bloka planirovaniya [Organizational and technological design in construction based on the intelligent planning block] // Vesntik grazhdanskih inzhenerov [Bulletin of civil engineers]. 2019. No. 6 (77). Pp. 193-199. URL: https://www.elibrary.ru/item.asp?id=42322352 (In Russian)
18. Zharov Ya.V. Informacionnoe modelirovanie stroitel`stva na ocnove blochnoklasternoy strukturi [Information modeling of construction based on block cluster structure] // Normirovanie I oplata truda v stroitel`stve [Rationing and payment of labor in construction]. 2019. No. 11. Pp. 10-14. URL: https://www.elibrary.ru/item.asp?id=42332282 (In Russian)
19. Lazareva N.V., Zinoviev A.Yu. O principah informatizacii stroitel`no-tehnicheskih ekspertiz [On the principles of Informatization of construction and technical expertise] // Promishlennoe I grazhdanskoe stroitel`stvo [Industrial and civil construction]. 2020. No. 7. Pp. 41-45. URL: http://www.pgs1923.ru/ru/index.php?m=4&y=2020&v=07&p=06 (In Russian)
20. Lazareva N.V., Zinoviev A.Yu. Effektifnost` organizacii pretenzionno-iskovoy raboti I stroitel`no-tehnicheskoy ekspertizi [Efficiency of the organization of claim work and construction and technical expertise] // Promishlennoe I grazhdanskoe stroitel`stvo [Industrial and civil construction]. 2020. No. 8. Pp. 60-64. URL: https://www.elibrary.ru/item.asp?id=43963241 (In Russian)
Review
For citations:
Lazareva N.V., Zinoviev A.Yu. Rationing of resources and time spent on work performed as part of construction and technical expertise. New technologies in construction. 2022;(4):41-50. (In Russ.) https://doi.org/10.24412/2409-4358-2022-4-41-50